Planning application
We are currently preparing a planning application, which is anticipated to be submitted later in summer 2026.
As part of the planning application process, we will submit reports to assess any potential impacts, such as:
Ecology
Landscape
Flooding
Noise
Heritage
Transport
June 2026
Public Consultation
Later in summer 2026
Submission of planning application
Autumn/Winter 2026
Determination of planning application
Spring/Summer 2027
Construction to commence